Concrete double wall (shear)

Double-sided concrete walls
 

Forming the walls is done by modular panels and always in the execution of a concrete wall
Three parameters were considered and the layout design was determined based on these parameters:
 
 Containment of the side pressure of the concrete. The height of the wall of stability. The set of molds of the two-way wall formatting system components
Is as follows:
1- Modular panels connected to each other by wedge and male.
2- Two-head bolts and between bolts of water tight, which are used for concrete pressures, which are between
The holes in the panels are covered with a bowl of chestnut and beetles, and by the double washers
Pipe and nut are connected to the vertical bundle of the pipe pair and their distance from the horizon
 1 meter and at a height of 0.5 meters, which can be used to save the high wall bolts to
Consider the distance of 1 meter (in height).
3. Scaffolding tubes that are positioned horizontally at a distance of 0.5 m (height) and
Connected to the panels by the medium clamp.
4 - The pilgrims are placed vertically and at intervals of 1 meter (on the horizon) from each other to control it
 Hydrostatic force.
5. Bolts of a cord connected by a bead and a bow tie to Solajr and Soljgar
Connects to the scaffolding (horizontal backs).